This maintenance project will include asphalt maintenance, accessible sidewalk curb ramps, minor curb modifications, and restriping.
Construction funding is provided by the Community Crossings Matching Grant program.
Project Timeline:
- Design: Spring 2023
- Construction: Summer/Fall 2023.
Bidding Documents:
Letting Date: March 13th, 2023
Zoom meeting link for Bid Opening- Click here
Bids are due in the City Hall Atrium by 11:50 AM on Monday, March 13th, 2023. Bids will be opened and read aloud at a public meeting, City Hall, 401 North Morton Street at 12:00 PM (Noon) on Monday, March 13th, 2023.
Bid Results:
Milestone Contractors, LP - $474,712.00
E & B Paving, LLC - $549,300.00