Project Summary:

This project is expected to include the following:

  • Replace the existing traffic signal equipment at the intersection of Rogers Street and Kirkwood Avenue.
  • Resurface the asphalt roadway along Kirkwood Avenue from Pine Street to Rogers Street.
  • Replace and improve pedestrian curb ramps and crosswalks along Kirkwood Avenue from Pine Street to Rogers Street.
  • Improve visibility along Kirkwood Avenue through minor on-street parking updates such as restricting parking near intersections.
  • Address an existing pattern of crashes by restricting left turn movements from alleys and driveways located between Jackson Street and Rogers Street.
  • Construct minor stormwater drainage improvements.

Kimley-Horn & Associates Inc. is the engineering design consultant for this project.

Project Timeline:

  • Design: 2025
  • Public Meeting: June 25, 2025
  • Construction: TBD 2026

Public Meeting Details:

Date: June 25th, 2025

Time: 5:30pm - 6:30pm

Location: City Hall Council Chambers, 401 N Morton Street 

Zoom Link for Virtual Attendance: Closed.

 

Project Documents:

See draft concept plans attached below.

Bid and Award Information:

  • Advertisement/Release: March 22nd, 2026
  • City's Procurement Portal
  • Letting Date: 12:00 pm local time on April 6th, 2026
  • Award Date: 5:30 pm on Tuesday, April 21st, 2026, in the Council Chambers of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and via Zoom by using the following link: https://bloomington.in.gov/boards/public-works.

Project Contact: