Project Details:

This project is a realignment of the existing paved pedestrian trail that will increase the accessibility and safety of its users. This will also create a safer shoulder slope along Moores Pike.

 

Project Timeline:

  • Design: 2023
  • Bid: Nov. 2023
  • Construction is expected to begin in March or April 2024

Project Documents:

(Disclaimer; all documents are for reference only. Official documents are located on OpenGov.)

 

Bid and Award Information:

  • Invitation to Bidders
  • Bidding Packet with Addenda
  • Addendum No.1
  • Addendum No.2
  • Letting Date: 12:00 pm EST Monday, December 4th, 2023 in the Council Chambers of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and via Zoom by using the following link: https://bloomington.in.gov/boards/public-works.
  • Award Date: December 5th, 2023, regular meeting of the Board of Public Works which will be held in the Council Chambers of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and by using the link provided above, or a subsequent meeting of the Board of Public Works.

 

Bid Results 12/04/2023

Crider & Crider, INC.         $142,168.00

E&B Paving LLC                  $166,860.50

Milestone Contractor, LP  $269,235.00

Project Contacts:

Zac Rogers, Project Manager, Engineering Dept.

812.349.3913 or zac.rogers@bloomington.in.gov