Project Details:

City of Bloomington will be modifying drives and adding approximately 360' of sidewalk along Liberty Drive south of West 3rd Street. This work will be adjacent to the properties located at 3477 West 3rd Street and 3535 West 3rd Street. This work will require removal and replacing the private entrances of these properties. 

Project Timeline:

  • Bid: Award Date December 19th 2023
  • Construction Spring of 2024
  • Completed April 2024

Project Contact:

Jeremy Inman, Project Manager

jeremy.inman@bloomington.in.gov

812-349-3913

 

Bid Amounts: 

Service Solutions of Bloomington Inc. $97,268.73

Groomer Construction Inc.                  $99,972.40

Crider & Crider, Inc                              $126,697.50

River Town Construction LLC              $139,485.00

Milestone Contractors, L.P.                 $190,491.00

E&B Paving Bloomington                    $196,519.00

On December 19, 2023 at the Board of Public Works meeting this project was awarded to Service Solutions of Bloomington for the amount of $97,268.73.  