City Construction Projects
423 E Kirkwood AVE
- Case Date:
- 7/2/1998
Mr. Madsen called to express his concern about the efficiency of tax money on the sidewalk sweeper the City just purchased. He believes the City merchants should sweep their own sidewalks, and in the winter should shovel their own walks to better promote people to use the dowtown area. This was just a general complaint to voice his concern.
City Construction Projects
401 N Morton ST
- Case Date:
- 9/5/1997
Steve does not understand why contruction projects around campus and the kirkwood area begin exactly when the students return to school. Why don't they start in the summer when there is much less traffic?
City Construction Projects
304 S Rogers ST
- Case Date:
- 8/28/1997
After traffic calming device was installed at the corner of 3rd and Rogers, sidewalk had to be realigned. Realigning meant tree had to be dug up and the lawn in this area was never fixed.
See letter
City Construction Projects
2535 W Evergreen DR
- Case Date:
- 6/12/1997
MR. LUCAS CALLED AND STATED THAT SEWER LINES WERE INSTALLED TWICE IN A YEAR (THE LAST BEING ABOUT 5 WEEKS AGO) AND THAT DAMAGE WAS DONE TO HIS PROPERTY AND HAS NOT YET BEEN REPAIRED.
City Construction Projects
2419 W Evergreen DR
- Case Date:
- 5/19/1997
DENNIS SISCOE IS BUILDING A HOUSE AT 2419 W EVERGREEN DRIVE. APPARENTLY HE HAD TO COME ACROSS THE FRONT YARD OF MR. LUCAS' HOUSE TO HOOK ONTO THE CITY SEWER. IT HAS BEEN OVER TWO WEEKS AND THE TRENCH HAS NOT BEEN PROPERLY COVERED. THERE IS SEVERAL ROCK AND DEBRIS IN HIS YARD. HE WANTED TO KNOW IF THIS LINE HAD BEEN INSPECTED AND WHAT CAN BE DONE TO MAKE SISCOE CORRECT THIS PROBLEM. REFERRED TO THE MONROE COUNTY BUILDING DEPARTMENT.
City Construction Projects
615 N Adams ST
- Case Date:
- 5/15/1997
8TH & ADAMS STREET REDEVELOPMENT PROJECT: HALL STATES THAT THE SIDEWALK IS SPALDING VERY BADLY. HE WOULD LIKE TO HAVE SOMEONE FROM THE CITY COME AND WALK THE SITE WITH HIM. HALL STATES THAT THIS IS "THE WORST JOB HE HAS EVER SEEN".
City Construction Projects
110 S Clark ST
- Case Date:
- 9/19/2001
Ms. Ritter stated that a street cut was done in front of her house and that the street cut has fallen in. She thought that the cut was made to repair a gas line, but said that the City made the cut?
City Construction Projects
401 N Morton ST
- Case Date:
- 5/25/2005
citizen querried in re plans for improvement for three locations: rodgers rd between sare and snoody, olcott in hyde park, and generally potholes throughout the city. said they were "aweful".
City Construction Projects
309 N Walnut ST
- Case Date:
- 6/16/1999
sidewalk torn up in the 300 block, in front of Taco Bell (think by gas company) and was never repaired. Has been out for awhile and is a hazard to pedestrians (Carol I also think they did not repair the sidewalk next to Alice's house on Morton and 10th. You may want to address both of these walks with them)
City Construction Projects
401 N Morton ST
- Case Date:
- 10/23/1997
Mr. Sutherland is frustrated and perplexed, that the City has the nerve to take on so many construction projects at one time, especially when all the students are back in town. He had to detour 4 different times just to get to work on the west side of town. He thinks this is very poor planning on the part of the City, and he'd like to know how all of this construction can be scheduled to take place at the same time?